Work Order
SOP/01351/23-24, Revision 1. Original work-order date: 30 September 2023.
AU-5 Revamp Unit • Petrochemical and Lube Integration Project (J-L8) • Gujarat Refinery
Cosmo Engineering Company completed piping works for the AU-5 Revamp Unit under the Petrochemical and Lube Integration Project “LUPECH” (J-L8) at IOCL’s Gujarat Refinery in Vadodara. The work order was issued by Sopan O & M Company Private Limited.
The work-order scope included piping fabrication and erection, valve installation, pipe-support and structural work, together with associated modification and dismantling activities.
SOP/01351/23-24, Revision 1. Original work-order date: 30 September 2023.
Material segregation, pipe preparation, fit-up, welding, inspection coordination and completion tracking across multiple metallurgy classes.
Completed in 2024 with the material-classified inch-dia quantities consolidated from the work-order BOQ.
The totals below consolidate the BOQ entries where material classification is explicitly identified.
MS includes Carbon Steel, LTCS, IBR Carbon Steel and Galvanised Carbon Steel. Unclassified modification and dismantling quantities are separately recorded and excluded. Piping erection recorded in inch-meter is also excluded from these inch-dia totals.
High-resolution views of the project’s pipe inventory, fabrication area and material-handling activity.